FG Responds to Public Outcry, Issues Tough Directives to China Harbour on Road Projects

Published

on


Joel Ajayi 


The Federal Government has taken decisive steps to address public complaints and enforce contractor accountability following a high-level meeting between the Minister of Works, Senator Engineer David Umahi, CON, FNSE, FNATE, officials of the Ministry and those of China Harbour Engineering Company (CHEC) and its sister company, China Harbour Operation and Maintenance Company (CHOMC), concessionaires on the Mararraba-Keffi-Akwanga-Lafia-Makurdi Dual Carriageway, held on Thursday, 5 February, 2026 at the Ministry’s Headquarters, Abuja.


During the meeting, several concerns relating to CHEC and CHOMC’s projects were reviewed, and firm warnings and directives were issued to safeguard public health, ensure quality delivery, and sustainability, also to protect government investment.


Engr. Umahi disclosed that the Ministry received a formal petition over the ongoing Makurdi-9th Nile-Enugu road project, where excessive dust from construction activities has continued to pose environmental and health risks to residents on the corridor.

 Therefore, he directed that the Permanent Secretary issue a letter to the contractor, mandating immediate dust-control measures, including soil stabilisation techniques, to be implemented. He warned that failure to resolve the issue within 7 days would lead to the project’s suspension.


On the Dualisation of the Mararraba-Keffi-Akwanga-Lafia-Makurdi Road, the Minister stated that although the project was started by the previous government, the present one completed some sections and tolled them. It was, however, observed that portions of the earlier completed road by the past administration were already falling.


 Consequently, he reiterated his previous directive that the first five (5) kilometres of the project must be milled, re-asphalted with concrete, and properly re-marked, stressing that the contractor has been given seven days to commence the work.


He further directed that other identified failed sections along the Dual Carriageway be properly rehabilitated through milling and overlay, with particular attention given to poorly executed areas around the Nasarawa State University, failed bridge expansion joints, damaged manhole covers, blocked drainage channels, washouts, and constant vegetation control.

In addition, he instructed that all road furnishings be reinstated after the maintenance works.
Engr. Umahi emphasised the need for improved highway safety management, directing the contractor to strengthen corridor monitoring and ensure the prompt removal of stationary vehicles to prevent obstruction and accidents on the Highways.


Whilst expressing deep concern over the slow pace of work on the 7th Axial Road project in Lagos, he noted that site mobilisation remains insufficient despite repeated engagements with the contractor at the site and in Abuja.

He highlighted that substantial mobilisation funds have already been paid to CHEC, yet key machineries have not been deployed with minimal site clearance being carried out. In this regard, he also warned that “If full mobilisation is not achieved within the agreed timeframe, we will recover the funds and take firm contractual action.”


The Minister made it abundantly clear that the Renewed Hope Administration of His Excellency, President Bola Ahmed Tinubu, GCFR will no longer tolerate poor execution, delays, or disregard for agreed standards, stressing that warning letters, withholding of certificates, and broader contractual consequences will be applied, where necessary.


He assured Nigerians that the Federal Government remains responsive to public concerns and committed to protecting lives, infrastructure integrity, and getting value for public funds.

He informed that President Tinubu is determined to enforce accountability and break away from practices that undermine national development.


Highlighting the administration’s inheritance of projects, Engr. Umahi stated that the government inherited 2,064 ongoing projects valued at more than ₦13 trillion as of May 29, 2023, excluding those on the Infrastructure Tax Credit Scheme. Despite funding constraints, road construction and rehabilitation are progressing nationwide, he confirmed.

While acknowledging that the entire federal road network cannot be completed within a single term of four years, the Minister expressed confidence that sustained tempo over the next five years would significantly transform Nigeria’s infrastructure.

He, therefore, urged Nigerians to massively vote for President Tinubu in 2027, in order to continue enhancing infrastructure and transportation as enablers of growth and much more.


Responding on behalf of the  management of the two companies, the Acting Executive Director (Operations) of CHOMC, Mr. Stephen Lee promised that industry-standard anti-dust measures will be taken on all construction sites, adequate mobilisation and full commencement of work on the 7th Axial Road and the rehabilitation of the failed sections of the Mararraba-Lafia road. 

The Minister concluded by reiterating that contractors must either meet agreed standards or face firm consequences, as the Federal Government remains resolute in delivering safe and durable road infrastructure to Nigerians.

Continue Reading

News

FG Commits To National Development With Major Contract Agreements — Umahi

Published

on

Joel Ajayi

The Federal Government, through the Federal Ministry of Works, has again signed landmark contract agreements with four (4) construction firms to execute critical road projects across the country, in line with the Renewed Hope Agenda of the administration of President Bola Ahmed Tinubu, GCFR. The contract signing ceremony, held on Thursday at the Ministry’s Headquarters in Mabushi, Abuja, marks another major step in the Federal Government’s commitment to delivering durable, sustainable road infrastructure that enhances connectivity, stimulates economic growth, and improves the quality of life of Nigerians.

The four contractors and their respective projects are as follows:

1. Messrs J. Patel and Sons Nigeria Limited – Reconstruction of Mando (Kaduna) – Birnin Gwari Road in Kaduna State,

2. Messrs JRB Construction Company Limited – Dualisation of Ibadan–Ijebu Ode Road in Oyo and Ogun States,

3. Messrs Truecrete Solutions Limited – Construction of Osogbo–Ikirun–Akoda Road in Osun State and

4. Messrs Peculiar Ultimate Concerns Limited – Construction of Osogbo–Iwo–Ibadan Road in Osun and Oyo States.

Speaking during the event, the Honourable Minister of Works, Engr. David Umahi, CON, FNSE, FNATE, described the projects as strategic national infrastructure designed to boost economic activities, improve transportation efficiency, and strengthen national integration. He noted that the reconstruction of the Mando (Kaduna) –Birnin Gwari Road in Kaduna State holds special significance, as it was one of the key infrastructure development commitments made by His Excellency, President Tinubu during the 2022/2023 electioneering campaigns. According to the Minister, the present administration remains resolute in its determination to deliver world-class infrastructure that will stand the test of time. “Our vision is to build roads that will last for generations. Under the Renewed Hope administration, we are determined to deliver infrastructure that can serve Nigerians for up to 100 years through the adoption of rigid pavement (concrete) technology,” Umahi stated.

The Minister commended the selected contractors for their competence, track records, and proven capacity, emphasising the Federal Government’s confidence in indigenous contractors. He particularly praised Messrs JRB Construction Company Limited, Truecrete Solutions Limited, and other indigenous firms for their commendable performances on previous projects across the country.

Umahi charged all contractors to mobilise to their respective project sites immediately and commence work without delay, stressing that the Ministry expects measurable progress within the stipulated timelines.

Earlier in his remarks, the Permanent Secretary, Mr. Rafiu Olarinre Adeladan, who formally signed the contract agreements, described the occasion as the successful completion of the procurement process and the official commencement of project implementation.

He commended the leadership of the Ministry for its commitment to ensuring that projects reached the execution stage and reaffirmed the Ministry’s dedication to effective monitoring, quality assurance, and timely delivery.

Also speaking, the Director of Highways, Construction and Rehabilitation, Mr. Clement Ogbuagu, presented details of the awarded contracts as follows:

1. Reconstruction of Mando–Birnin Gwari Road, Kaduna State

Contractor: Messrs J. Patel and Sons Nigeria Limited

Contract Sum: ₦178,116,787,162.00

Length: 122 Kilometres

2. Dualisation of Ibadan–Ijebu Ode Road, Oyo and Ogun States

Contractor: JRB Construction Company Limited,

Contract Sum: ₦295,996,609,992.77

Length: 114.5 Kilometres (Single Carriageway Equivalent)

3. Construction of Osogbo–Ikirun–Akoda Road, Osun State

Contractor: Truecrete Solutions Limited

Contract Sum: ₦101,806,585,825.90

Length: 70 Kilometres (Single Carriageway Equivalent) and

4. Construction of Osogbo–Iwo–Ibadan Road, Osun State

Contractor: Peculiar Ultimate Concerns Limited

Contract Sum: ₦114,854,477,607.93

Length: 73 Kilometres

All the projects will be executed using Continuously Reinforced Concrete Pavement (CRCP) technology, in line with the Federal Government’s commitment to building durable, cost-effective, and sustainable road infrastructure nationwide.

The ceremony represents another significant milestone in the Federal Government’s drive to modernise Nigeria’s road network and accelerate national economic development.