Non Compliance: FG Terminates Rehabilitation Of Abuja-Kaduna-Zaria-Kano Dual Carriageway With Julius Berger

Published

on


Joel Ajayi 


Federal Ministry of Works on has terminated Rehabilitation of Abuja-Kaduna-Zaria-Kano Dual Carriageway in FCT, Kaduna and Kano States, Contract No.6350, Section I (Abuja-Kaduna) with Messrs Julius Berger (Nig.) Plcover non compliance.


In a statement issued in Abuja by the ,Director, Press and Public Relations of Ministry of Work, Mohammed A. Ahmed reveals that, after the Management meeting of the Ministry  which is borne out of several months of going back and forth without any meaningful progress was reached.


According to the statement, Based on non-compliance with reviewed cost, scope and terms, stoppage of work and refusal to remobilise to site, as directed, the Federal Ministry of Works has issued a 14-day Notice of Termination to Messrs Julius Berger (Nig.) Plc for the Rehabilitation of Abuja-Kaduna-Zaria-Kano Dual Carriageway in FCT, Kaduna and Kano States, Contract No.6350, Section I (Abuja-Kaduna),  today, 4th November, 2024. 


“The decision, which is borne out of several months of going back and forth without any meaningful progress was reached at a   Management meeting of the Ministry. The Ministry has in the last 13 months been in constant talks with the company, in order to reach an amiable position on the said alignment but to no avail.


“Nigerians may wish to know that the Contract for the Rehabilitation of the Abuja-Kaduna-Zaria-Kano Dual Carriageway, which was divided into three (3) Sections was awarded to the company on 20th December, 2017 and flagged off by the then Minister of Power, Works and Housing, H:E. Babatunde Raji Fashola at an initial  sum of N155.748,178,425.50 billion(One Hundred and Fifty-Five Billion, Seven Hundred Forty-Eight Million, One Hundred and Seventy-Eight Thousand, Four Hundred and Twenty-Five naira Fifty Kobo) on 18th June, 2018.

Sections II (Kaduna – Zaria) and III (Zaria – Kano) were partially completed and handed over during the twilight of the administration of former President  Muhammadu Buhari, GCFR. 
“Since then it has been one variation and augmentation or the other and finally, the present Minister of Works directed for the redesigning and re-scoping of the Section I of the contract. 


“The alignment was divided into two with one phase redesigned to be on continuously reinforced concrete pavement (CRCP), while the remaining with asphaltic pavement. Approval for the Section I, Phase 1 for a length of 38 (thirty-eight) kilometres on concrete pavement was given to Messrs Dangote Industries (Nig.) Ltd, while the remaining 127 (one hundred and twenty-seven) kilometres remained with the substantive contractor. The Phase 1 was flagged off on 17th October, 2024 with a 14-month completion period.


“Due to the stalemate of the contract and, most importantly, the desire of His Excellency, President Bola Ahmed Tinubu, GCFR, as encapsulated in the Renewed Hope Agenda infrastructure initiative, to see to the completion of this laudable project, also to alleviate the sufferings of Nigerians plying the road, the Ministry re-scoped it and got the approval of the Federal Executive Council (FEC). “


The statement added that: “The award for the Re-scoping and Downward Review of Contract for the Rehabilitation of Abuja-Kaduna-Zaria-Kano Dual Carriageway in FCT, Kaduna and Kano States, Contract No.6350, Section I (Abuja-Kaduna) in favour of Messrs Julius Berger (Nig.) Plc from the sum of N797,263,523,738.87 (seven hundred and ninety-seven billion, two hundred and sixty-three million, five hundred and twenty-three thousand, seven hundred and thirty-eight naira  eighty-seven kobo) to N740,797,204,173.25 (seven hundred and forty billion, seven hundred and ninety-seven million, two hundred and four thousand , one hundred and seventy-three naira twenty-five kobo) was granted by FEC on 23rd September, 2024 and conveyed to the company on 3rd October, 2024. 


“As due to the socio-economic importance the road as a vital artery connecting Abuja, the FCT to the North, the Ministry conveyed the approval for a Final Offer on the Abuja – Kaduna Dual Carriageway to the company on 23rd October, 2024, stating that it should agree, in writing, to accept the reviewed contract sum of N740,797,204,173.25 (seven hundred and forty billion, seven hundred and ninety-seven million, two hundred and four thousand , one hundred and seventy-three naira twenty-five kobo) within seven (7) days or risk the termination of the said contract. It is a sad commentary on the Company that rather than accepting the offer, they tinkered with the Bills of Quantities, as well as that of Engineering Measurements and Evaluation via a letter to the Ministry dated 29th October, 2024.


“The company was summoned for a meeting with the Management of the Ministry, today, 4th November, 2024 but refused to show up, hence the termination of the contract  based on effluxion of time and non- performance.”

Continue Reading

News

FG Commits To National Development With Major Contract Agreements — Umahi

Published

on

Joel Ajayi

The Federal Government, through the Federal Ministry of Works, has again signed landmark contract agreements with four (4) construction firms to execute critical road projects across the country, in line with the Renewed Hope Agenda of the administration of President Bola Ahmed Tinubu, GCFR. The contract signing ceremony, held on Thursday at the Ministry’s Headquarters in Mabushi, Abuja, marks another major step in the Federal Government’s commitment to delivering durable, sustainable road infrastructure that enhances connectivity, stimulates economic growth, and improves the quality of life of Nigerians.

The four contractors and their respective projects are as follows:

1. Messrs J. Patel and Sons Nigeria Limited – Reconstruction of Mando (Kaduna) – Birnin Gwari Road in Kaduna State,

2. Messrs JRB Construction Company Limited – Dualisation of Ibadan–Ijebu Ode Road in Oyo and Ogun States,

3. Messrs Truecrete Solutions Limited – Construction of Osogbo–Ikirun–Akoda Road in Osun State and

4. Messrs Peculiar Ultimate Concerns Limited – Construction of Osogbo–Iwo–Ibadan Road in Osun and Oyo States.

Speaking during the event, the Honourable Minister of Works, Engr. David Umahi, CON, FNSE, FNATE, described the projects as strategic national infrastructure designed to boost economic activities, improve transportation efficiency, and strengthen national integration. He noted that the reconstruction of the Mando (Kaduna) –Birnin Gwari Road in Kaduna State holds special significance, as it was one of the key infrastructure development commitments made by His Excellency, President Tinubu during the 2022/2023 electioneering campaigns. According to the Minister, the present administration remains resolute in its determination to deliver world-class infrastructure that will stand the test of time. “Our vision is to build roads that will last for generations. Under the Renewed Hope administration, we are determined to deliver infrastructure that can serve Nigerians for up to 100 years through the adoption of rigid pavement (concrete) technology,” Umahi stated.

The Minister commended the selected contractors for their competence, track records, and proven capacity, emphasising the Federal Government’s confidence in indigenous contractors. He particularly praised Messrs JRB Construction Company Limited, Truecrete Solutions Limited, and other indigenous firms for their commendable performances on previous projects across the country.

Umahi charged all contractors to mobilise to their respective project sites immediately and commence work without delay, stressing that the Ministry expects measurable progress within the stipulated timelines.

Earlier in his remarks, the Permanent Secretary, Mr. Rafiu Olarinre Adeladan, who formally signed the contract agreements, described the occasion as the successful completion of the procurement process and the official commencement of project implementation.

He commended the leadership of the Ministry for its commitment to ensuring that projects reached the execution stage and reaffirmed the Ministry’s dedication to effective monitoring, quality assurance, and timely delivery.

Also speaking, the Director of Highways, Construction and Rehabilitation, Mr. Clement Ogbuagu, presented details of the awarded contracts as follows:

1. Reconstruction of Mando–Birnin Gwari Road, Kaduna State

Contractor: Messrs J. Patel and Sons Nigeria Limited

Contract Sum: ₦178,116,787,162.00

Length: 122 Kilometres

2. Dualisation of Ibadan–Ijebu Ode Road, Oyo and Ogun States

Contractor: JRB Construction Company Limited,

Contract Sum: ₦295,996,609,992.77

Length: 114.5 Kilometres (Single Carriageway Equivalent)

3. Construction of Osogbo–Ikirun–Akoda Road, Osun State

Contractor: Truecrete Solutions Limited

Contract Sum: ₦101,806,585,825.90

Length: 70 Kilometres (Single Carriageway Equivalent) and

4. Construction of Osogbo–Iwo–Ibadan Road, Osun State

Contractor: Peculiar Ultimate Concerns Limited

Contract Sum: ₦114,854,477,607.93

Length: 73 Kilometres

All the projects will be executed using Continuously Reinforced Concrete Pavement (CRCP) technology, in line with the Federal Government’s commitment to building durable, cost-effective, and sustainable road infrastructure nationwide.

The ceremony represents another significant milestone in the Federal Government’s drive to modernise Nigeria’s road network and accelerate national economic development.